As part of the Township's annual capital improvements, Robert Place, Edward Avenue, Banta Avenue, Peck Avenue and Prospect Avenue will be milled and resurfaced beginning Wed., Sept. 14, 2022. Please see more detailed information on the schedule below.
Milling Operations:
- Robert Place – 9/14/22
- Edward Avenue – 9/14/22 & 9/15/22
- Banta Avenue – 9/15/22
- Peck Avenue – 9/16/22
- Prospect Avenue – 9/16/22
Paving operations are tentatively scheduled for next week as follows:
- Robert Place, Edward Ave and Banta Ave now on Monday, September 26, 2022
pushed back again due to weather Friday, September 23, 2022 was initially was Tuesday the 20th - Peck Ave, Prospect Ave now on Tuesday, September 27, 2022
pushed back again due to weather Monday, September 26, 2022 was initially Wednesday the 21st, depending on the weather.
Vehicular access will be limited during milling operations and restricted during the paving.
Please feel free to contact the Township Engineer’s Office if you have any questions or require additional information.