Weather permitting, the paving of Hillview Road (Beaverbrook Road in Lincoln Park) will begin Monday, April 13 (NOW 4/20), 2020, between the hours of 7:00 AM and 5:00 PM. During active construction, the road will be closed except for local traffic.
On Monday, April 7, 2020, the Township received notification from the contractor that the work will be initiated on Monday, April 20, 2020. The revision is noted below.
Please see the Map of the Project that includes the section of the road to be closed and recommended detour.
The schedule is anticipated, as follows:
- April 13 – Milling NOW APRIL 20, 2020
- April 14 – Paving NOW APRIL 21/22, 2020
- April 15 – Rain Date(s) as needed NOW APRIL 23, 3030
Drivers who are unable to avoid the work area should watch for construction/detour signs and for directions from Police Officers or Public Works staff. Please be aware of moving equipment, traffic directors, and the safety of workers in the road.
Access to residential driveways will be limited. Should you have concerns about a period of critical access, please feel free to notify the Township Engineer or Director of Public Works a minimum of one hour prior to leaving or arriving. Every reasonable effort will be made to provide accessibility.
The Department of Public Works/Engineering Division officials ask anyone with questions or concerns about the roadway improvement project to call the Engineering office.
Please remember the inconvenience is temporary, but the improvements are permanent. We appreciate your patience during this construction project.